BEFORE: BATHROOM DEMO. PHASE II BEGINS...
/It's Christmas day for momma. Demo has begun! The dumpster arrived this morning (15 yarder) which is $170 plus $95/ton. I wanted to share what I'm anticipating my net costs to be. This should be pretty accurate as everything has been priced out + I have all of the material finalized and here:
- Dumpster: $300
MASTER
- Light Fixture 192
- Tub 950.00
- Vanity Base 1099
- Vanity Top 1250
- Shower Door 1000
- Trim/Valves 1873
- Electrical 750
- Plumbing 1,800
- Carpenter/Tiling 5,730
- Extra Hardware 200
- Paint 400
- Marble Tile 2516
KIDS - Vanity Base / Top 1350
- Trim/Valves 1144
- Ceramic 245
- Electrical 750
- Carpenter/Tiling 2850
- Extra Hardware 200
- Tub reglazing 250
- Paint 400
- Marble Tile 1012
- Plumbing 1800
SUM $28,061